what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?

Answer Posted / bhupendra potpose

Consumption & Rate analysis RCC(Cement Concrete) 1:2:4

Providing and placing cement concrete excluding formwork &
reinforcement
1.475 Ref: Always use 1..475 standard
Proportion of materials
(1440 Kg / Cum ) Cement 1
(Dry 1600 Kg / Cum & Wet 1850 Kg /Cum ) Sand
2
(1650 Kg / Cum ) Metal 4
Total 7
Std constant(1.5) / Total of proporttion(7)
0.211
1) Required volume of cement for 1 cum
1 Proportion of cement 0.211
Add wastage 2.50% 0.005
Vol of cement for 1 cum 0.216
0.035 is cum qty of per 50kg of bags, no of bags
0.035 6.171
Cost of cement per bags 325
Total of -1, cost of bags 2005.5
2) Required volume of Sand for 1 cum
2 Proportionof Sand 0.421
Add wastage 2.50% 0.011
Vol of Sand for 1 cum 0.432
Cost of sand per Cum 2125
Total of -2, cost of sand 917.9

3) Required volume of Aggregate for 1 cum

3 Proportionof Metal 0.843
Add wastage 2.50% 0.021
Vol of Metal for 1 cum 0.864
Cost of Metal per cum 975
Total of -3, cost of metal 842.3

A- Total of (1+2+3), cost of Material (Concrete)
3765.8

4)Cost for Manpower ,Mixing ,Shifting & Machinary ,
0.35%
B-Total of -4, Cost of Labour per cum (35%)
13.2

C-Total of (A + B) cost of Material & Labour
3779.0

5) Add Over head if any 5% 188.95
6) Profit 15% 595.19
D- Total of (A+B+C)cost P/A 1:2:4 Concreting
4563.12

Is This Answer Correct ?    8 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM

2646


Explain what is change order request?

679


how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend

1593


by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)

1689


What is the material consumption- cement,sand,tiles etc for Toilet dado?

7050






1)What is the total volume of aggregates required for 1cu.mtr.solid hard concrete? 2)What is total mass of wet concrte and dry concrete after 28 days of M25? 3) Is 28 days strength is the final strength of concrete or it gets increasing as the time period increses.? 4)What is the volumetric proportion of concrete grade of M25.M30,M35,M40

2255


What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?

2243


How do you prepare Material Recovery Statement for deduction from contractors bills?

1101


HOW SOON CAN YOU TRAVEL DON TO ANY LOCATION POSTED U?

2036


What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?

2105


sir, whitch is the best book (writer name) for prepration of gate....

1206


How to calculate quantity of plum masonry in 1:3:7

2519


what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????

1623


plumbing CPVC fitting FTE Brass full form

2130


why demand factor less then 1 ?

1769