how can we calculate the amount of concrete in trapezoidal
footing?
Answer Posted / ajay saini
if the area of base is A1 and the area of top is A2 then the volume=h/3(A1squr+A2squr+under the rootA1xA2)
nOW QUANTITY(KG)=Volume x Density of concrete
the density of concrete Varies on different conditions but we can take this 1500-2350 kg/cum
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
reinforcement slab, beam and column formulas?
WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?
Basic questions of civil engineering
What is the difference between built area and super built up area?
how much one carpenter can doing shuttering of slab in one day
What is missing report and how to prepare
The largest size of paper used in plotter to print the drawing made by Autocad .
what post do you prefer to work in this company and why do you think you can serve better in such position?
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
Which Types Of Bricks ?
how to calculate the strength of rebound hammer test reading in building construction ?
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?
Can we apply curing compound on ceiling (slab Bottom)
How many % we consider for lap for reinforcement for estimates