how can we calculate the amount of concrete in trapezoidal
footing?
Answer Posted / prashant verma
if A is length and B is breath and H is total height of trapezoidal footing and a' and b' is size of column n h is trapezoidal portion height.
then total qty of concrete is=A*B*(H-h)+[{h/3{a^2+b^2+(ab)^1/2}]
where a=A*B
b=a'*b'
| Is This Answer Correct ? | 6 Yes | 2 No |
Post New Answer View All Answers
what is tension footing?
If u want ur Ans.Of any Question so mail me skatiyar011@yahoo.in
2nd and 4rt angle elevation used in which country ?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
How to find out kg per Sft ?
what is the construction cost for per cft of multistorryed building in kolkata?
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
how to determine H- zone in a column? where it will occur?
IS code for Rolling Margin of steel
Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa
material required for construction of 1cu.mtr wall (Cement, No of bricks (Brick size 40cm x 20cm x 10cm),sand,Quantity of water
What are the joints wants to made in masonry where door opening, arches like etc..
I am called for interview from north east power plant .so, I need some interview question which may help me.
what is pouring and explain