how can we calculate the amount of concrete in trapezoidal
footing?
Answer Posted / prashant verma
if A is length and B is breath and H is total height of trapezoidal footing and a' and b' is size of column n h is trapezoidal portion height.
then total qty of concrete is=A*B*(H-h)+[{h/3{a^2+b^2+(ab)^1/2}]
where a=A*B
b=a'*b'
| Is This Answer Correct ? | 6 Yes | 2 No |
Post New Answer View All Answers
cement and sand required for one block of size 0.23*0.15*0.46
What is the difference between Grade I, II and III of GSB?
Why nautical mile is different from statute mile?
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
What is the tensile strength of marble?
How to take labor charges for construction of 1cum of concrete?
what is stressing
How can we make a hole in a solid rectangle using solidsworks?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
How do you calculate the unit weight of concrete?
For fine aggregate which is most suitable River sand or crusher sand & why ?
can we compare the combined core of DBM and BC density with average density of Lab DBM and Lab BC density
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
how to find out hard strata in bored pile when the DMC method adopted.