How much used for sand per square meter in 12mm Thickness
Answer Posted / mahesh
if it is a saturated sand then 1*1*.0120=.012cum*1920kg/cum=23kg of sand if it is a dry sand then 1*1*.0120=.012cum*1780kg/cum=21.36kg.
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
What is rolling stock
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
If u want ur Ans.Of any Question so mail me skatiyar011@yahoo.in
The portion of a brick cut across the width is called?
What are segregation and bleeding?
what is pouring and explain
How to estabilish reinforcement Steel rolling margin for a building projects ?
what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
Mention different types of roof systems?
How is improve my knowledge in construction industries....
How to activate isometric axes in cad?