What is the difference between nominal mix and design mix?
Answer Posted / er. bikash kumar deo ,civil en
Nominal mixes are those proportioned by the volume of the main ingredients and usually written in order of the ingredients thus Cement:Sand: Coarse aggregate (stone, chippings). So a 1:3:6 is a nominal mix containing 1 volume of cement, 3 volumes of sand and 6 volumes of coarse aggregate.
Gauge boxes are generally used to batch the ingredients. The problem with these types of mixes is that the quality of the concrete is entirely dependant on the quality of the materials. In other words, if you use the same gauge boxes to weigh ingredients from different sources, you will most likely have different concrete qualities.
Designed mixes on the other hand are specified as a grade the producer of the concrete has to achieve usually in terms of compressive strength but may include other criteria (size of the stone, minimum amount of cement, flexural strength, air content etc). So a grade 30 concrete will be the same whether batched in Kansas City, Karachi, Kingston-Upon-Hull or Kinshasa
Is This Answer Correct ? | 7 Yes | 8 No |
Post New Answer View All Answers
What are the applications of cad?
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
Floor tile measurement? Wall to wall or skirting to skirting
brickwork labour rate per cum ?
what is pouring and explain
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.
punj loyed and sapurjl palanjl
how much quantity of cement,sand and water required for 1 sq feet flooring work .
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
What are the advantages of building a dam on the river nile?
whou haat goals do you have in your career
How we calculate the service time of buildings