How to calculate lap,bond and hook length for preparing bar
Bending schedule ?
Answer Posted / mohammed aijaz hussain.
Lap length: 45 diameter of the bar (in compression member)
50 diameter of the bar (in tension member)
Bond length: 24 diameter of the bar
Hook length: 12 diameter of the bar
| Is This Answer Correct ? | 68 Yes | 31 No |
Post New Answer View All Answers
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
Moisture content calculation for diff mix ratio's ??
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
How is improve my knowledge in construction industries....
Define What is a projection line?
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
What is the absolute pressure scale?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
What is the exception critarea of cube?
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
The 4 main factors to start a construction project are––
what is the mix design for M:60 with micro silica andmetakaoline?
How many cum of 9.5mm stone in 1 ton ?
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete