Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by volume).

Answer Posted / wajahat

dry mix volume=1*1.5=1.5m^3
volume of sand=1.5*(2/7)=0.4285m^3

Is This Answer Correct ?    6 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

2073


Where will be the maximum bending moment in a TEE Beam?

7413


In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:

3436


What is the procedure of concealed plumbing in toilets?

2289


hai, kindly send anyone for output workers format details for construction project in foundation to finishing.

1461


What are the advantages of cad software?

1070


How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)

2196


115mm thickness brick work how to required mortar

2006


What are the advantages and disadvantages of using plastic and timber fenders?

1096


what else we can add rather than admixture in concrete to reduce the cement quantity?

6097


what is the theoritical percentage of concrete cubes testing per day?

5027


how to design and calculate materail quantity for concrete speedbreaker ?

5912


how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab

2393


trapozidal

2439


what is the water cement ratio for plastering

1590