what,s the clear cover of beam,slab,column,lintel and
foundation?
Answer Posted / vasanth.j
concrete Nominal clear cover details for some structures
1.Slab 15mm
2.Column 40mm
3.Beam 30mm
4.Footing 40mm
Clear cover is also depend on the corrosion free and fire resisting for reinforcements.
| Is This Answer Correct ? | 33 Yes | 32 No |
Post New Answer View All Answers
What are the techniques to measure road difference?
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
How much percentage of brick bats allowed in CD-75 bricks
what is relation between SPT N value and driving piles after conducting a soil test?
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
What is the purpose of the gap in the road on this bridge?
What are the methods of measurement? Describe it shortly
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
what is the meaning of degreasing of the euipment or line.
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
Why Is Propping Required For Long Structures Once The Form Work Is Removed?