how can we calculate the cutting length of 10,12,16,20 and
so on iron bars for 45 digree and 90 digree bents plz tell
me if there is any formula or tabel to find it
Answer Posted / bikash bhowmick
for calculation of cutting length deductions for 90 degree bend is......cutting length= total length- 2* dia of bar(upto 20) and 3*dia of bar when bar dia 25 and above......
| Is This Answer Correct ? | 43 Yes | 11 No |
Post New Answer View All Answers
what are the changes in concrete pour height as per IS 456, 2009?
what is the max. area can we apply the plate load test ?
How to calculate the quantity of cement mortar 2" for mosaic tile fixing 12"x12"?
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
How to determine thee cut length for steel reinforcement bars in R.C.C design
Explain what is Hybrid Foundation?
What difference comes in constructing of house and a housing complex like society
TELL US ABOUT A TIME WHEN YOU FAILED TO MEET A DEAD LINE. WHAT WERE THE REPERCUSSIONS?
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
What is the sugested procedure of water purification for public supply?
what is the name of shuttering oil used in oman
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
How many types of slabs are there & how to design it?
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.