Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what do you mean by ssd how it calculated

Answer Posted / manoj

SSD - Saturated surface dry defined as the condition of an
aggregate in which the surfaces of the particles are
saturated

1)have no water on their surface, which will be added to
the free water content.
2)will not absorb any free water in the time between the
mixing and the setting of the concrete.
It is therefore the condition of the aggregate, which
ensures that the aggregate will not affect the free water
content.

Is This Answer Correct ?    9 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2840


What are the causes of building collapse?

1143


what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?

2273


What do we mean by partial moment release ??

3870


What you understand by richter scale?

1189


What is the coeffiencent Friction Angle between Steel and Ashphalt?

2990


what is called the inverd level of mabhole chamber?

2105


How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?

1521


What is Time period of a building and its relation with frequency ?

1422


Explain what is progress payment?

1133


1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM

3162


What are the advantages and disadvantages of using plastic and timber fenders?

1134


What is difference between engineering stress and true stress?

1153


60-70 grade of Bitumen is VG-30 ?

2093


How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton

2100