What is the quantity of cement, sand, and gravel to be used
in M20 grade of concrete for 1000 x 1000 x 1000 mm of sand
(for cement please mention in kilos, and for sand and
gravel please mention it in CFT)
Answer Posted / k.raja
Correction in Question we made:
What is the quantity of cement, sand, and gravel to be used
in M20 grade of concrete for 1000 x 1000 x 1000 mm.
(for cement please mention in kilos, and for sand and
gravel please mention it in CFT)
1000mmx1000mmx1000mm =1 mx1mx1m = 1cum ok
M20 Grade =1:1 1/2:3
summation of proportion=1+1.5+3=5.5
1.54cum of dry materials of concrete will yield only 1 cum
concrete after adding water.
1cum x1.54/5.5= 0.28 cum
so cement = 0.28cum x 1440 = 403.5 kg
sand = 0.42cum x 10.47 = 4.40 cft
aggregate = 0.84cum x 10.47 = 8.80 cft
Is This Answer Correct ? | 3 Yes | 10 No |
Post New Answer View All Answers
Any strength is a stress but any stress is not strength
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
What are the applications of the modulus of elasticity?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
Describe the advantages and disadvantages of using plastic and timber fenders?
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
Which type of plywood & sizes using in construction projects ?
Forces in a Shear Wall are in plane or out of plane ?
How to calculate unit weight of concrete for m40 grade.
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
What is Refuse Area In High Rise Building ?
What is the origin of name railway sleepers?
how beam.coloum ,slab, footing are designed as per indian code.. detail procedure?
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.