Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

I heard Thump rule about beam depth is 1" per 1' length. Is
this correct? If not please tell me the thump rule.Thanks.

Answer Posted / amreeta

no it is to calculated like
100mm depth per 1m span ..when the total depth(D) is not
given.
after you get the total depth(D)
then calculate effective depth(d)
d = D-(cover of the beam +radii of the rod)

assume cover = 20-25mm
dia of the rod 16-20mm

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is proportion of PCC Grade G?

2028


In block work seawalls what is the purpose of slip joints?

1215


what do you understand by M25 concrete

2416


What is the distance between railway tracks?

1238


How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?

2064


What expenses counted in contingencies and how much it is in related to built-up area of the building.

1760


I have to conduct load test on greting cover, pressure gauge is in kg cm2, how to caluculate load on this greting cover.

2305


Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.

2386


how many tonnes equals to one cubic feet?

1658


how to do sudoko puzaals?

2259


I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations

1472


How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument

2147


why building got air crack? if it get in one particular are what is means?

2445


Explain what is the difference between built area and super built up area?

1172


how to caluclate sienerge qty in construction in ap

2426