in the footings first which reinforcement bar has to be
layed as per design criteria.
Answer Posted / vincent
long span must lay first for the footings but in slab short span comes first
| Is This Answer Correct ? | 15 Yes | 2 No |
Post New Answer View All Answers
Define line type?
Wats the formula of eccentric footing and how was calculated from concrete qty
how do you calaculate the total steel quantity of an rcc building using thumb rule?
What is the material consumption- cement,sand,tiles etc for Toilet dado?
please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
Formula for calculating the volume of bulb in underreamed pile
What is unit weight of normal concrete?
List out the potential risk factors for workers on the construction site?
How many days should curing of plastering, brick work and concrete
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')
What is the standard volume of pharma in cub ft
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
how much cement sand n bricks required in im3?and how much in plaster?