what is the formula of calculating number of bars?
Answer Posted / sobhanbabu
((total length-clear covers of both sides)/spacing)+1
| Is This Answer Correct ? | 34 Yes | 4 No |
Post New Answer View All Answers
what is the max. area can we apply the plate load test ?
punj loyed and sapurjl palanjl
How many mortar required for Brickwork of 1 Cu.m works??
What are the uses of layer?
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
Concrete cover for slab, column, beam and footing?
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
please send me bhel questions on rupesh.017@rediffmail.com
What do you mean by bond? What are the different types of bonds?
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
States some of the commonly used commands in cad software’s?
How will you Engage Labours on Site?
What is Time period of a building and its relation with frequency ?