what is th consuption of cement , sand in plastering for 15mm
thick cm1:4,1:3
Answer Posted / arjun
For 15mm Thick Cement Plaster:
In CM 1:3 cement Consumption is 8.772 Kgs/Sqm (0.172*510)
Sand is 0.18404 Cum/10Sqm (0.172*1.07 per 10 Cum)
In CM 1:4 cement Consumption is 6.536 Kgs/Sqm (0.172*380)
Sand is 0.18404 Cum/10Sqm (0.172*1.07 per 10 Cum)
| Is This Answer Correct ? | 2 Yes | 13 No |
Post New Answer View All Answers
pls tell me , what is the water content
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
how to take concrete quantity for precast segment for viaduct project?
What is Grid floor and mention its advantages ?
how to estimate material requirement for an area of house in square feet?
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
How to find CN by using arcgis 9.3?
What is demising walls?
Civil engineering material testing Standard results
WHAT IS YOUR EXPECTED SALARY?
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?