Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

beam top main reinforcement(25mm) was drilled off by
mistakely when making drill hole for dummy columns. any one
can give useful information for this issue or related code
or websites.

Answer Posted / suresh baria

Remove the top covering of beam, Observe the laying of top
reinforcement then drill the hole of required dia berween
the top reinforcementof beam for the errection of
reinforcement of dummy columns.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate brick work quantity?? Block work quantity??

2522


explain what do you mean by the property development.

2093


how to calculate the concrete mix m30 by volume

1549


How you can use different dimension tools in cad? What are the different dimensions available?

1155


how to calculate MR 9(derivation)

2956


how to calculate the density for high density concrete ? or is it same as the density of RC?

2428


I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent

2227


Formula for calculating the volume of bulb in underreamed pile

5033


The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?

2231


WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

2031


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

2453


how to disign cuplock shuttering and it's matireal requirement snd any related web site

3030


Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.

3490


hi guys what happens if you are absent for a supplymentry exam?

1838


hai, kindly send anyone for output workers format details for construction project in foundation to finishing.

1522