beam top main reinforcement(25mm) was drilled off by
mistakely when making drill hole for dummy columns. any one
can give useful information for this issue or related code
or websites.
Answer Posted / suresh baria
Remove the top covering of beam, Observe the laying of top
reinforcement then drill the hole of required dia berween
the top reinforcementof beam for the errection of
reinforcement of dummy columns.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
How to calculate brick work quantity?? Block work quantity??
explain what do you mean by the property development.
how to calculate the concrete mix m30 by volume
How you can use different dimension tools in cad? What are the different dimensions available?
how to calculate MR 9(derivation)
how to calculate the density for high density concrete ? or is it same as the density of RC?
I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent
Formula for calculating the volume of bulb in underreamed pile
The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
how to disign cuplock shuttering and it's matireal requirement snd any related web site
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
hi guys what happens if you are absent for a supplymentry exam?
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.