how to calculate cement bag in RCC
Answer Posted / shibu
cement concrete 1:2:4 using 20 mm broken stone for
reinforced concrete works.1 m3
20 mm stone=0.9 m3
sand=0.45/ m3
cement=330 kg/m3
Is This Answer Correct ? | 13 Yes | 3 No |
Post New Answer View All Answers
is there any influence of water(used for mixing of concrete) on a weight of harndend concrete.
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?
please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
How to calculate sand , cement quantity for 23mm thk brick work(10x10)
Material calculation of cm 1:6 for 1sqm
What is the difference between a wood shake and wood shingles?
How do you maintain water pressure?
What are the responsibilities of a site manager?
what is Brest Wall?
why we use aggregate,sand with cement in concrete?
pls tell me about method of cutting length of ties column
Mention what are the composition of a landfill?