Answer Posted / devendra_kushwaha27
When an AC excitation signal is applied to the Primary Coil
(P), voltages are induced in the two Secondary Coils (S).
The MAGNETIC CORE inside the COIL WINDING ASSEMBLY provides
the magnetic flux path linking the Primary and secondary
Coils.Since the two voltages are of opposite polarity, the
Secondary Coils are connected series opposing in the
center, or Null Position. The output voltages are equal
and opposite in polarity and, therefore, the output voltage
is zero. The Null Position of an LVDT is extremely stable
and repeatable.
When the MAGNETIC CORE is displaced rom the Null
Position, an electromagnetic imbalance occurs. This
imbalance generates a differential AC output voltage
across the Secondary Coils which is linearly proportional
to the direction and magnitude of the displacement.
As shown in the figure, when the MAGNETIC CORE is moved
from the Null
Position, the induced voltage in the Secondary Coil, toward
which the Core is
moved, increases while the induced voltage in the opposite
Secondary Coil
decreases.
LVDTs possess the inherent ruggedness and durability of a
transformer and
truly provide infinite resolution in all types of
environments. As a result of the
superior reliability and accuracy of LVDTs, they are the
ideal choice for linear
motion control.
LVDT Principle of Operation Page 1 of 2
http://www.
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
Explain the difference between plc and cnc?
How r the calculation of process line mpm.
what is the procedure of belt scale calibration?
How can you add value to this Industry if offered the job?
why Fahrenheit unit of moistur analyzer transmitter
what is installation and commissioning of (fat & sat) of power plant dcs ? this question keeps in desirable conditions of one company .
Give 2 application of quartz crystal used for process parameter measurement.
How to do gas analysers calibration in AUTO and Manually by using zero and span gas?
What are different type of instrument cable
who's take first position in process in the timing of new installation flow transmitter and control vavle. give the answer with logical trick.
sir ,iam in dem urgent need of HPCL Paper of Instrumentation Branch plz send me at your earliest convenience at ujjwal_sharma1983@yahoo.com
how pressure transmitter work, what is its principal to measure and how its generate signal. for pressure transmitterinstallation which precautions must be taken ??
How u will setup SPI(2007) on Citrix Server (Thin Client Mode)? Plz Justify?
what is output of FOUNDATION FIELD BUS transmitter
Why ac supply load cell is used? Can we use the dc supply load cell?