Any body tell me how can we calculate 1m3 quantity of cement
sand aggregrate in kg.
Answer Posted / krishna kumar.a
Example : concrete 1:2:4
Coarse aggregate =95% of volume =0.95 cum.
Fine aggregate = 50 % of coarse aggregate =0.475 cum.
Cement = 50 % of Fine aggregate =0.2375 cum.
=0.2375 * 1440 kg./ cum
=342 kg.
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
explain what do you mean by the property development.
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
construction workers how much time take one work or qty
why we use aggregate,sand with cement in concrete?
What is the different type of slump test indications?
What is the l/d ratio of cantilever beam?
What are the uses of alloys in daily life and how are alloys made?
How to activate isometric axes in cad?
insted of bentonite we can use any alternate material in piling ?
Define What is the tallest man made structure in the world?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?