in built up area basis what is ratio of concrete & steel
ratio may be consider in per sqft quantity
Answer Posted / abhishek
1=7.5
| Is This Answer Correct ? | 6 Yes | 2 No |
Post New Answer View All Answers
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
Calculation of curtain wall of box culvert
What is GSB gradation
Basic questions of civil engineering
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
What in your past experience or education prepares you for the position for which you are applying
hi guys what happens if you are absent for a supplymentry exam?
1m square 20mm plastering how much of water need curing work
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
What are new methods /technologies of pothole patching?
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
How long does it take concrete to harden?