What is vector group? What is meant by DYN11?Why is it needed?
Answer Posted / ahmed koriem
Simply
the capital letters are for the HV side whether it is the primary or secondary
and the small letters are for the lv side either primary or secondary
Y or y means star
D or d means delta
N or n meas neutral outgoing from the Trans.
11 means that HV side lag lv side by 30° as HV is the reference and lv is at 11 O'Clock and as we know that the positive direction is anti-Clock
wise then lv leads HV
or 11 O'Clock happens before 12O'Clock and the same result is concluded.
| Is This Answer Correct ? | 17 Yes | 6 No |
Post New Answer View All Answers
sir, iam a electrical engg graduate and i want to go in automation sector and for this i have decided to do industrial training for this,plz suggest me some good institute for the same in delhi,ncr. my degree percentage is 58%, can i get job after doing training, plz help....
Meaning of ingrace protection for motor.for ex IPXY
How can i get my certificate of competency as an electrical supervisor? I have complicated my B.Tech from Uttarakhand technical university this year (2012).
Why arc quenching is used in Diode ?
What are books to be referred for KPTCL exam?
1))why we run three phase or three different circuit from a single conduit 2)) why not two circuit of different phase run in same conduit?? and why we run same three cicuit of same phae run in single conduit??
IF DISTANCE IS 100METERS B/W AMP.METER AND CURRENT TRANSFORMER WHAT WILL BE AFFECT IN ACCURACY .METER CAN SHOWING ACCURATE CURRENT OR NOT IF NOT WHAT CAN I DO TO GET 100% ACCURACY.
being an electrical engineer why you wanna come into software i have an very good academics what answer i have to give
Block diagram of Power line communication?
how do u gauge the size of the cable ?for eg. consider a 300 sqmm L.T Cable.How do u determine the size of the cable seeing it pratically?
Why auxiliary transformers are not connected in parallel in primary stations?
I am having dual speed motor of cromton greaves make of 3.7 KW -1400 rpm and 5 KW - 900 rpm. Please let me know groups and winding connction for rewinding purpose.
why the NGR (neutral grounding resistor) always OFF during DG off?
sent to a site and asked to explain how you would like a twenty seven flour building should be supplied with lighting and sockets plus a water boiler.
can anybody tell me that for p.f. Improvment we use capacitor banks but how to decide its capacitance. As we all know how to calculate kvar but what abt capacitance value