What is a BBS?Find out the cutting length for a 300*300 column with 40 mm cover?
Answer Posted / vishal s rao
BBS is Bar Bending schedule
For 300*300 size column
rings will be 300-(40*2)=220mm
220mm on 4sides i.e =880mm
for bending purpose on two end 75mm to be kept.
i.e 880+75+75=1030mm
For right angle 2*d to be added.
i.e 2*8*4=64mm
So totally = 1030+64=1094mm.
| Is This Answer Correct ? | 14 Yes | 22 No |
Post New Answer View All Answers
How to determine spacing of bars in slabs or beams
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?
can we use PPC for concrete wall, If yes, what is the concrete (PPC & OPC) grade for Non- load bearing concrete wall, load bearing concrete wall & for cellar retaining wall.
what is escalation?how it is done?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
WHAT DLC DESIGN IN CONSTRUCTION
Why joints are provided?
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
How many pyramid in egypt?
What are the uses of layer?
What is proportion of PCC Grade G?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
Describe a time when you anticipated potential problems and developed Preventive measures
What is Time period of a building and its relation with frequency ?
Define Who designed the city of Washington DC?