What is the difference between M20 and M25 concrete?
Answer Posted / k.shivakumar
M20 - Mix 20 is the Grade of concrete which attains its
compression strength of 200kg per sqcm or 20Ner sqmm or
20Mpa after 28days of casting of concrete
M25 - Mix 25 is the Grade of concrete which attains its
compression strength of 250kg per sqcm or 25 N per sqmm or
25Mpa after 28days of casting of concrete
hence the difference is only 5
| Is This Answer Correct ? | 69 Yes | 1 No |
Post New Answer View All Answers
for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
Explain major difference between auto level and dumpy level?
what is the service corridor?
what does the track parameter mean in staad.pro?
what is directivity effect?
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
How do we test on design and style in a software?
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
What is the per cu. mt. price of ready mix in Gujarat region.?
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
How can you achieve soil enforcement?
Which type of plywood & sizes using in construction projects ?
what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15