Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Explain about SOURCING & SINKING concepts in PLC to field
sensor wiring ?

Answer Posted / asad

Sourcing mean we are giving +ve from the field and -ve is common through PLC and sinking mean we are giving -ve from the field and +ve is common through PLC

Is This Answer Correct ?    7 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Why even multiple power supplu r used in instrumentation system?

4981


what is loop1 and loop2 in MTS LT?

4655


can you provide me full detail about instrumentation in ONGC??

2166


what is the electrical operation procedure for switching on 27.6MVA electric furnace.

2030


key phaser where is use and work

1972


How to Calibrate Flammable gas detector in field

1211


Draw a wheatstone bridge circuit showing supply, meter and 3 wire RTD connection

2015


Why rdt and thermocouple both give different output .and one things more, how to generate  ohm or mili volt  plz mail me merajalam143545@yahoo.com

2806


Can anybody please let me know Orifice plate sizing calculation formula and step by step procedure

1994


what is the input to be given in digital flow meter during the the calibration time?

2226


Explain types of valves?

1055


why we r opening HOT BYPASS valve during startup of a compressor?

2094


State bernoulli’s application.

1141


A PLC is programmed to drive three motors A, B and C as follows : After running motor A for an hour, motor B should get ON and motor A should get OFF. And after running motor B for an hour, motor C should get ON and motor B should get OFF. And after running motor C for an hour, motor A should get ON and motor C should get OFF. (That is, a cyclic repetition with time period one hour) Now, the second condition is: If any motor gone faulty and is tripped, the consecutive motor should get ON and the faulty (tripped) motor should be eliminated from cyclic repetition. The remaining two motors should bear the cyclic repetition of one hour each. (For healthy motor take logic as high and for tripped motor take logic as low) Now, the third condition is: When motor A load(Amps) exceeds 60% of its rated load, motor B should get ON in parallel to motor A. And when both motors A & B are running in parallel, and if their load exceeds 60% of their rated load, motor C should also start in parallel to A & B. [Here the cyclic repetition is eliminated, until their loads become normal(40%)] [Take logic high(1) for load at 60% and logic low(0) for load at 40%] Now draw a flow chart or a ladder diagram to fulfill the above condition.

2174


To become an Instrument DESIGN engineer, is there any softwares or training to become Instrument Design engineer, plz suggest me, Iam very much interested in designing.

3465