Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what is the pre commissioning test to be carried out on LT power panel at site?

Answer Posted / arasusulo

checking the all of bus
bars tightness and visual
short at phase to phase and
neautral...
then megger the separate
phase and ntral bus too.
then circiut braker
condition tooo.then charge
the supply and check ph
voltage and line voltage.
switch on the braker then
dstrbt the suppply by the
feeder what it is..?

Is This Answer Correct ?    19 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why the NGR (neutral grounding resistor) always OFF during DG off?

3425


My load is 1635 KW. & current pf is 0.884, I have to improve it for 0.99.Please suggest what KVAR value is needed?

1552


If we have 11 kv RYB Phase single core cable near about. Then wht effect and losses

1819


A powerplant has 8 gensets operating in grid parallel mode. In one genset sometimes there is pf variation and kvar variation. The plant operates in pf mode. When this variation is observed the load is stable, voltage is also stable, freq and genset speed is also stable. How will you check the functioning of pf card. What shall be the ideal output vdc of the pfc, from there it is input to AVR?

2269


Whether it is possible to measure energy at the input of rectifier transformer (12 pulse with very high odd harmonics)

1844


How is the speed of a DC shunt motor related to the armature current?

1129


in an electronic tri vector meter when the current and voltage sequence changes ? what is the effect of phase sequence on recording of meter

2163


why we are not giving the zone 1 trip command to the master trip relay

1684


WHAT IS AIR GAP VALUE IN MM FOR A 11KV BUSHING OF 11KV/440V DISTRIBUTION TRANSFORMER. AND AIR GAP VALUE OF 25 KV BUSHING OF AT TRANSFORMER OF 25 KV TRACTION. WHAT IS THE CALCULATION FOR THE AIR GAP PERMITTED FOR BUSHINGS AT DIFFERENT VOLTAGES.

3431


describe the Operation of induction generators from bus bars

2260


How to reduce the static electricity producing in solvent room? By P.D.Patil BioCon

2026


draw 3 phase rectifier diagram

2135


what is the operating time for LBB and how does the LBB relay realise whether cb is opened or not?

1928


i have install 750 kva distribution transformer at my site and want to do neutral earthing. what calculations should i follow to determine earthing conductor material and size?

2003


Why collecting electrode of ESP to be earthed

2070