Volume of concrete = 1 cu.ft.
Volume of Dry concrete = 1.5 X 1 = 1.5 cu.ft.
Volume of cement required = 1/ 5.5 X 1.5 = 0.273 cu.ft.
= 0.22 Bag = 11 kg.
Volume of sand required = 1.5/5.5 X 1.5 = 0.41 cu.ft.
Volume of aggregate = 3/5.5 X 1.5 = 0.82 cu.ft.
Is This Answer Correct ? | 19 Yes | 8 No |
Post New Answer View All Answers
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
How much for the BRC lapping in full yield and half yield < and which table to get it ?
What is change order request?
Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
what is kribs is supporting?
How much time Required for PPR pipe network testing
How do you determine specific gravity of cement?
During reclamation how can the occurrence of mud waves can be rectified?
psc girder detail
How many cum of 9.5mm stone in 1 ton ?
five requirements of infill panels for walls?
what is right & short method of measurement of slab&beam
what is concrete canvas?
Spider cracks occur in beam bottom due to––