I need to plaster an area of 1500 square meter. how much
quantity of cement and sand need for this.?
Answer Posted / mohammed aijaz hussain
Let the thickness of plastering be 12 mm and CM(1:4)
Volume of wet mortar = 12 mm X 1500 sq.m.
= 18 cu.m.
Add 20% for depressions, joints and wastage
= 3.6 + 18 = 21.6 cu.m.
Volume of Dry Mortar = 1.3 X 21.6 = 28.08 cu.m.
Cement required = 1/5 X 28.08 = 5.62 cu.m.
= 160.6 Bags
Sand required = 4/5 X 28.08 = 22.46 cu.m
Is This Answer Correct ? | 49 Yes | 5 No |
Post New Answer View All Answers
Pls explain me about tension and compression in a flat slab
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
What is meaning of FREE STANDING STAIRCASE ?
115mm thickness brick work how to required mortar
What do you mean by tolerance factor of concrete ?
Where is the worlds longest elevator and how long is it?
what is column foundation
Explain what is change order request?
What is meant by dimensioning?
For the construction project what capital cost has to be taken in consideration?
how to estimate material requirement for an area of house in square feet?
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
Why steel rods are produced only in even dimensions?
Consumption of Binding wire for fixing of cover block in vertical surface