Answer Posted / mohammed aijaz hussain
Splicing is the increasing of the steel bar by over-lapping
like 45d in case of compression member and 50d in case of
tension member, where 'd' is the diameter of the steel bar.
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
is there any influence of water(used for mixing of concrete) on a weight of harndend concrete.
what is the composition of good brick ?
why +1 to be followed for calculating the no of bars in BBS. Please explain
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
what does the grad of cement shows (denotes)?
What is meant by scaffolding coefficient?
What is the different type of slump test indications?
in staad ,why we realease a moment of a member ? what is affect if we realease a moment
What is Critical path in Ms-Project ?
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
What is the release of lien?
What materials were used to build the golden gate bridge?
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??