what"s the formula find the cement consumption for brick work
23 thick wall 1 m3?

Answer Posted / mohammed aijaz hussain

Volume of Dry Mortar = 35% of volume of Brickwork

Let the Cement Mortar Proportion be CM(1:4)

Volume of mortar required = 0.35 X 1 = 0.35 cu.m.

Cement required = 1/5 X 0.35 = 0.07 cu.m. = 2 bags

Sand required = 4/5 X 0.35 = 0.28 cu.m.

Is This Answer Correct ?    46 Yes 22 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How do you measure concrete?

766


Who built the sears tower?

637


Why reinforcement done in shorter span in two way slabs

1374


How to fix toll charge for a particular vehicle at toll booths in a highway?

1489


what is education Cess.

1738






What is the use of water table & Kreb stone for drain

1367


Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish

2091


Differentiate first angle & third angle projection?

650


satart to end steps by step process of building construction...? i want to planning theme accuretly

1444


how much percent are used 20mm,10mm?

1438


How many Sft of Level Plaster per Kg

1121


How to find permissible diagonal tensile stress in reinforced brick work

2071


what is mc arther pile?

1775


what is polity

1649


For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.

1588