how much quantity are required like cement,sand,aggregate
for (46*29*0.41)feet slab? how much this quantity can be
calculated?
Answer Posted / asad ali
wet volume conc: = 546.94 cu.ft
lets supposed ratio of conc: = (1:2:4)
sum of ratio = 7
first we find dry volume according to nature
dry volume of con: = 546.94*1.54 = 842.287cu.ft
1.54 is constant for conc: and 1.27 is constant for mortar
after a that we find cement,sanda and crush quantity OK
quantity of cement = ratio of cement *dry volume
--------------------------------
sum of ratio
this is the formula OK
= 1*842.287/7
=120.32 cu.ft OK
in bags of cement
we know that one bag of cement = 1.25cu.ft
so there fore 120.32/1.25 = 96.26 bags
say 96.5 bags
quantity of sand = ratio of sand * dry volume / sum of ratio
= 2*842.287 = 240.65cu.ft
quantity of crush = ratio*dry volume / sum of ratio
= 4*842.287/7
= 481.306cu.ft OK
quantity of cement = 96.5 bags
quantity of sand = 240.65 cu.ft
and last one
quantity of crush = 481.306 cu.ft
OK OK Ok Ok Ok any Question about contact me
civil.com7875@yahoo.com
Is This Answer Correct ? | 12 Yes | 0 No |
Post New Answer View All Answers
plz drive the formula d2/162.162 for the calculation of weight of steel bars????
silt%= silt volume/ silt+sand volume is this right?
what do you understand by M25 concrete
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
please give the detail design for the soring and shuttering for 8.5m deep excavation in the sandy soil for 25x10 rectangular streaches
Why Vitrified tile are getting pop up.
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
density of crush sand & crush stone or grit powder
How much quantity of cement,sand,stone used to build 1 cum of cc road??
What is OSHA compliance?
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
Gidc technical que paper
what is parametre for M25 after 7 days strength
satart to end steps by step process of building construction...? i want to planning theme accuretly
sir how can we find the cement and sand required for making 4" drop