hi i am working in a civil Lab .....they asked me to find
out the compressive strength of concrete cubes after 7 days
of curing....the value of load on CCT machine is 205KN how
to convert it to Kg/cm2 ....plzz help me...........
Answer Posted / asad ali
let suppose you have given cube size is (6*6*6 inch)or(15*15*15 cm) OK
we know we that 1N = 1kg.m/sec.sq.....(1)
first we convert KN to N OK
25KN = 25000N
according to physical equation F=ma or W=Mg......(2)
m=mass , g= gravitational force = 9.81m/sec.sq OK
so according to eq (1)
25000N=25000kg.m/sec.sq
there fore divide the (g) \
25000kg.m/sec.sq
---------------------- = 2548.41kg OK
9.81m/sec.s
and the given area of cube = 15*15 = 225cm.sq
stress in conc: cube = 2548.41kg
-----------
225cm.sq
stress = 11.326Kg/cm^2
OK
Is This Answer Correct ? | 6 Yes | 5 No |
Post New Answer View All Answers
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
How do we determine the specific gravity of a cement?
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
How is the leaning tower of pisa supported?
Explain different types of rcc pipes.
What does civil engineering mean?
How can you distinguish between sorption, absorption and adsorption?
What is dead load impact load live load
types of survey and levelling instrument ?
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers
Why Should Curing Not Be Done By Ponding And Polythene Sheets?
wat would be the probable interview questions and GD topics for IOCL exam?
How much quantity water should be placed in one cubic meter area?
What does a construction cost covers and what does not?