hi i am working in a civil Lab .....they asked me to find
out the compressive strength of concrete cubes after 7 days
of curing....the value of load on CCT machine is 205KN how
to convert it to Kg/cm2 ....plzz help me...........
Answer Posted / asad ali
let suppose you have given cube size is (6*6*6 inch)or(15*15*15 cm) OK
we know we that 1N = 1kg.m/sec.sq.....(1)
first we convert KN to N OK
25KN = 25000N
according to physical equation F=ma or W=Mg......(2)
m=mass , g= gravitational force = 9.81m/sec.sq OK
so according to eq (1)
25000N=25000kg.m/sec.sq
there fore divide the (g) \
25000kg.m/sec.sq
---------------------- = 2548.41kg OK
9.81m/sec.s
and the given area of cube = 15*15 = 225cm.sq
stress in conc: cube = 2548.41kg
-----------
225cm.sq
stress = 11.326Kg/cm^2
OK
| Is This Answer Correct ? | 6 Yes | 5 No |
Post New Answer View All Answers
What is the worlds largest concrete dam?
How does a traffic light signal work ?
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
What does civil status mean?
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
Define What are the uses of Groynes?
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
yasser arfatcompleted his degree in civil from which university
What is difference between engineering stress and true stress?
how the calculation occurs if i want to mix 1cum of M50 concrete. please calculate every ingredients with detail calculation.
Stringer How many cm goes to landind
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
rate analysis for cement pointing 1:4 , for 100 sq m