what"s the formula to find the cement,sand,aggreegate(45mm)
requirement for PCC?
Answer Posted / ajith
1 Cement 4 Sand and 8 Coarse aggregate
One M3 of PCC hence requires 0.076923 M3 of Cement
0ne M3 Cement =1440 Kg
0.076923 X 1440 = 110.7692
Or 2.22 Bag of Cement
| Is This Answer Correct ? | 17 Yes | 9 No |
Post New Answer View All Answers
CAST EFFECTIVE WATER SUMP CONSTRUCTION DETAIL
Calculation of Pier Cap with tapper area?
Difference between pre-tensioning and post-tensioning.
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
what do you mean by yeild stress of a material? What will happen when hit is given to cement?
Explain what is 1/8 on the architect ruler denotes?
How much wastages taken in 1. cement 2. steel 3. fine aggregate 4. coarse aggregates (10mm, 20 mm)
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.
what is BPM in concrete demolition hammers. what is better a higher value or lower
what is civil enginnering & what you need of this course?
Define What is the distance between railway tracks?
why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed