how many m3, mason should done per day if he going to build
4.5 inch brick work(partition wall)?
Answer Posted / surinder pal ( moga )
It is about 6cum
| Is This Answer Correct ? | 0 Yes | 4 No |
Post New Answer View All Answers
important question on stones
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
what is escalation?how it is done?
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
what is the difference between replacement of cement by groundnut shell ash
What is structural frames or systems?
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
Dear Sir What is the Contraction joint for base Slab
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
How much qty of stone ; sand; cement in R/R stone masonry of 136 CUM
Whats the meanig of ,'K' VALUE in the case of soil.....
Describe the advantages and disadvantages of using plastic and timber fenders?
What is costing in 100squre feet bricks
What is a bearing capacity of soil?