how to calculate quantity of steel & concrete in stair case
Answer Posted / saurabh kumar
first,we calculate length of waist by using pythagores rule
and this length multiply by width of waist and multiply by
thickness of waist slab.now for landing,length of landing
multiply by width of landing and multyply by thickness .we
add quantity of waist & landing which will be total
quantity of stair case
| Is This Answer Correct ? | 21 Yes | 8 No |
Post New Answer View All Answers
i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr
how we calculate the grade of the Bituminous materials.?????
use ofr concrete as per grade ?
what is the productivity in aluminium shuttering per day
PL.tell me about civil engineering questions with answer
What do you mean by honeycomb in concrete?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
how much area can be platered by a mason for exterior
satart to end steps by step process of building construction...? i want to planning theme accuretly
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?
How to calculate carrying capacity of the existing water supply trunkmain
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?
how much cement and sand required for 1cum rr masonry
What is difference between limit state and working stress method? How it is applies in building structure.