how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / chetan patel
for 1 cmt cont.of 1:1:2
cement:1.52/4=0.38/.035=10.8
Sand :0.38 cmt
Agg :0.38*2=0.76 cmt
So for 731/35.31=20.70 cmt
C :20.70*10.8=224 bag
S :20.70*0.38=7.86 cmt
A :20.70*0.76=15.73 cmt
| Is This Answer Correct ? | 8 Yes | 4 No |
Post New Answer View All Answers
How much for the BRC lapping in full yield and half yield < and which table to get it ?
what is kribs is supporting?
How many pyramid in egypt?
why steel tanks are provided (a) for water pressure (b) for wind pressure (c) for earthquake pressure
brickwork labour rate per cum ?
How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''
What is the outturn of Ceiling plastering
Is it possible to make a feature using an overdefined sketch?
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
What is meaning of tlc
can stub column take the load as main column
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
what is pqc