Answer Posted / xyz
The effective stress is reduced due to upward movement of
flow of water. When the head causing upward flow is
increased, a stage is reached when the effective stress is
reduced to zero. The condition so developed is known as
quick sand condition. Quick sand is not any special type of
sand, but it is a condition of zero effective stress in
cohesionless soils.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?
Explain moment of inertia and its importance.
how we calculate the grade of the Bituminous materials.?????
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
in one SQM plaster how much Cement and sand consumed in ratio 1:4
What is the exception critarea of cube?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
what is hydrostatic paradox?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
what is cross hair cursor?
What is reinforced concrete?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
In Abutment walls (A1 side) why we are adopting fixed bearing (POT-PTFE)?
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
What is Rankine Cycle?