how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.

Answer Posted / sumanth

we can only calculate the quantity in m3 only after that we
can converet in c.ft.
1/4 x 1.54 x 28.8= 11.08 bags cement for 1 m3 for the ratio
of 1:1:2
s0 731 cft = 20.719 m3 * 11.08 = 229.570 bags cement used
1/4 x 1.54 = .385 m3 sand for 1 m3
so 20.719 m3 x .385 = 7.976 m3 sand required in 731 cu .ft
2/4 x 1.54 = 0.77 m3 chips ( aggregate ) for 1 m3
so 20.719 m3 x 0.77 = 15.953 m3 chips required in 731 cu .ft

Is This Answer Correct ?    15 Yes 10 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How do you compute the volume of airflow?

671


Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.

1621


Why nautical mile is different from statute mile?

720


A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L

1544


Does VDF add strength to the flooring apart from preventing water ingress?

1054






LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.

1604


On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??

2830


what is moment-curvature relationship in semi rigid connections??

1653


what is pqc

1286


how statics is different from dynamics

1234


percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters

1627


What is the use of array command?

685


What is 1/8 on the architect ruler denotes?

638


door and window wood work calculations and different methods

1658


how much cost of single coat 20mm thick plastering per sqre meter

1053