what would be the rqmnt. of cement and sand (1:6)for
building brick wall and also 20mm thick plaster on the wall
by same ratio?
Answer Posted / p.rambabu
1.approximately we can calculate the requirement of brick
work for 1cum of 1:6 ratio
ans:cement=(1/6)*1440=239.999*0.21=50.399/50=1.007bags/cum.(here
the ratio of 0.21is the approximately dry volume of sand).
2.for 20mm thk plastering calculation,
a.first we can calculate the volume of plastering area,
b.increase it's volume to 20% because of the honeycomb
work& miscellaneous works.
c.multiply this value with dry volume of 1.3.
for 1:6 for 20mm thk of 100sq.m
cement=(1/7)*1.3*2.2=0.408*1440=587.52/50=11.750bags.
| Is This Answer Correct ? | 2 Yes | 3 No |
Post New Answer View All Answers
I what know about life time of frp tank plz explain about it specifications & other details
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
what is meant by shear center?????
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?
How to do rate analysis for concrete work including shuttering work?
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
Why should appointment store person for project ? what is the benefits for company ?
who to find building iron rod strenth
List out some of the checking’s, done at the completion of construction?
How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?
What ingredients with% found in ppc cement??
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
What you understand by building codes?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.