it's proportion for exampal 1:4, the parts of cement 1 and parts of sand 4.
now,
qty of cement per cu.meter from mortar= 1*1/(1+4)=0.2 cu.meter
qty of sand per cu.meter from mortar= 4*1/(1+4)= 0.8 cu.meter
| Is This Answer Correct ? | 11 Yes | 20 No |
Post New Answer View All Answers
Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?
what is the meaning of 40/20 src
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
How do we calculate the power of centrifugal pump?
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
what is moment-curvature relationship in semi rigid connections??
what are the values of compressieve strenght?
What are the types of slump?
What is a hatch patterns?
How to arrive dry volume of concrete (1.52 to 1.57) ?
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
how to calculate rate analysys of 1:6 plastering 10 sq m
What is the tensile strength of marble?