Answer Posted / abhishek
Main difference between DCS and PLC is about the scanning
time. PLC's have a fixed scanning time whereas DCS
execuation order(scanning) can be varied with certain
minimum limit. Generally a PLC can have a scan rate of as
low as 5msec(fixed) to some where around 20msec(fixed). As
DCS handles larger number of inputs/outputs its scanning
rate is 50msec and this value needs to be defined (can be
kept more than 50msec) while writing a program. But latest
DCS can have scanning rate of 20msec.
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
Which language of programing is popular? how can i learn it ?
Linear amplifier.
2. What is ultrasonic flowmeter?
i am having information technology branh ....... can i prepare for psu exam
How to Calibrate Ultrasonic Level Transmitter in field
why we are using magnet for calibration of gas detector?
WHAT IS THE DIFF. BETWEEN SKIN TEMPERATURE AND PASSES TEMPERATURE..?
in mass flow meter what is drive friquancy ?
Give Detail information about plc,dcs,and scada system?
What is the use of gauge?
What is the use of single seated valve?
How can i test procedure grounding for CAT-7 cable? Or How can we test procedure CAT-7 Cable Electrically safe?
what happen if i increase height of displacer type LT.accuracy or sensitivity are affected.why?
send me HPCL paper
What is the function of solenoid valve in on/off & shutdown valve and why it is not used in control valve normally?