Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Explain the STLC?

Answer Posted / muhammad abid

The different stages in Software Test Life Cycle -

Requirement Analysis
Test Planing
Test Case Development
Environment Setup
Test Execution
Test Cycle Closure

Each of these stages have a definite Entry and Exit criteria ,Activities & Deliverables associated with it.
In an Ideal world you will not enter the next stage until the exit criteria for the previous stage is met. But practically this is not always possible. So for this tutorial , we will focus of activities and deliverables for the different stages in STLC. Lets look into them in detail.
Requirement Analysis
During this phase, test team studies the requirements from a testing point of view to identify the testable requirements. The QA team may interact with various stakeholders (Client, Business Analyst, Technical Leads, System Architects etc) to understand the requirements in detail. Requirements could be either Functional (defining what the software must do) or Non Functional (defining system performance /security availability ) .Automation feasibility for the given testing project is also done in this stage.
Activities
• Identify types of tests to be performed.
• Gather details about testing priorities and focus.
• Prepare Requirement Traceability Matrix (RTM).
• Identify test environment details where testing is supposed to be carried out.
• Automation feasibility analysis (if required).
Deliverables
• RTM
• Automation feasibility report. (if applicable)

Test Planning
This phase is also called Test Strategy phase. Typically , in this stage, a Senior QA manager will determine effort and cost estimates for the project and would prepare and finalize the Test Plan.
Activities
• Preparation of test plan/strategy document for various types of testing
• Test tool selection
• Test effort estimation
• Resource planning and determining roles and responsibilities.
• Training requirement
Deliverables
• Test plan /strategy document.
• Effort estimation document.

Test Case Development
This phase involves creation, verification and rework of test cases & test scripts. Test data , is identified/created and is reviewed and then reworked as well.
Activities
• Create test cases, automation scripts (if applicable)
• Review and baseline test cases and scripts
• Create test data (If Test Environment is available)
Deliverables
• Test cases/scripts
• Test data

Test Environment Setup
Test environment decides the software and hardware conditions under which a work product is tested. Test environment set-up is one of the critical aspects of testing process and can be done in parallel with Test Case Development Stage. Test team may not be involved in this activity if the customer/development team provides the test environment in which case the test team is required to do a readiness check (smoke testing) of the given environment.
Activities
• Understand the required architecture, environment set-up and prepare hardware and software requirement list for the Test Environment.
• Setup test Environment and test data
• Perform smoke test on the build
Deliverables
• Environment ready with test data set up
• Smoke Test Results.

Test Execution
During this phase test team will carry out the testing based on the test plans and the test cases prepared. Bugs will be reported back to the development team for correction and retesting will be performed.
Activities
• Execute tests as per plan
• Document test results, and log defects for failed cases
• Map defects to test cases in RTM
• Retest the defect fixes
• Track the defects to closure
Deliverables
• Completed RTM with execution status
• Test cases updated with results
• Defect reports

Test Cycle Closure
Testing team will meet , discuss and analyze testing artifacts to identify strategies that have to be implemented in future, taking lessons from the current test cycle. The idea is to remove the process bottlenecks for future test cycles and share best practices for any similar projects in future.
Activities
• Evaluate cycle completion criteria based on Time,Test coverage,Cost,Software,Critical Business Objectives , Quality
• Prepare test metrics based on the above parameters.
• Document the learning out of the project
• Prepare Test closure report
• Qualitative and quantitative reporting of quality of the work product to the customer.
• Test result analysis to find out the defect distribution by type and severity.
Deliverables
• Test Closure report
• Test metrics

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What types of testing is specifically important for web testing?

1205


send the senario template

1957


I want to do certification in ISTQB please anybody hepl me with the details and site to refer for further details.............if possible give me the material as well on my mail id a.vishwakarma@aol.com. Please help me........Thanks

2218


how is market for testing in banglore,chennai,pune,delhi?

2274


What is the limit for test steps?It should be 10/20/30etc

1987


What is mean by incident logging system ?

2605


What do you plan to become after say 2-5yrs (Ex: QA Manager, Why?)

2199


When should you opt for manual testing over automation testing?

1232


how to write the test cases for mark as read/unread mails for gmail inbox?and what are the testings we will do?

6667


How do you Prepare a Defect Managemnt Policy

2088


HI FRNDS, I HAVE 2.5 years OF exp In Manual Testing,Plz let me know if thr r any oppurtunities in any company in Bangalore ID:dsnithi@gmail.com Thanks in Advance

2190


ive been looking for a junior tester job for quite some time now, but most company keep requisting for experienced staffs, but if i dont start from somewhere how do i get the experience

1920


What are testing techniques? What is difference between general and specific?

2269


What are the factors affecting a manual testing project and what are the ways to overcome it?

1275


How much the bug is affecting the functionality of the application?

1120