Cost control in civil construction as well as Quality control
Answer Posted / d. karthick
Safety First, Quality Best, Progress Must. If we follow the
above wards, we can able to complete the Project on Time.
During the Project we can not control the cost of concrete,
steel and other Project material (Only thing we can control
the wastage). But we can control the Overhead Cost for P&M,
Staff salary and other temp. works by completing the
project before the dead line
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
what is the productivity in aluminium shuttering per day
Explain what are the phases inspections are done by local authority while construction?
Define What is the origin of name Railway Sleepers?
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
Which code is used for tor & tmt steel bar?
What things you need to take care of before building a kitchen island?
Write short note on construction programme for pile foundation.
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
What are the skills required to become an architect?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
Define What is the tensile strength of wood?
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.