Please explain about FAT? What is the difference between
FAT and SAT?
Answer Posted / ajay
FAT: it is the acronym of Factory acceptance test i.e.
Tests performed under simulated conditions at
manufacturer's place witnessed by approving authority
client/End user.
FAT is performed to check the correctness of the system
being supplied. FAT covers all checks over hardware,
interfaces, logics & control loops and system configuration
as per the procedure defined in FAT document.
FAT is performed for Control/DCS & PLC panels.
SAT: it is the acronym of Site acceptance test i.e. tests
performed under live signals received from instruments
installed in plant during the actual commissioning of the
system at site/ end user's place. During SAT, all live
signals are checked and individual control loops & logics
are performed accordingly.
Once all individual loops and logics are checked, then only
plants process is left to run through control system itself.
Is This Answer Correct ? | 20 Yes | 1 No |
Post New Answer View All Answers
What is the difference between mmwc and mmwg?
Dear Sir/Madam,im going to attend Hpcl written exams on feb 17th in instrumentation stream..can anyone send me the HPCL model papers and pattern of HPCL ....i ve not yet attended anything in HPCL...so i dont know how it comes...so just i need some model test papers and pattern ..pls help me friends...
why we are using drum level control valve air to close?
How to calibrate displacer type level transmitter (chemtrol make )for level measurement in hotwell , LP & HP heater ?
what is maxdna ?. explain about the software details.
how is work pressure switch& level switch?what is the principle of this?
If P will increase then what will happen with PID?
Hi, I am Newely Joined in Construction company instrument engineer? Any one can Plz tell me How can I advanced preparation for Releated Engineering and construction Documents?
I am having a Phoenix digital to modbus converter. The o/p of the same is connected to flow computer FB407. But the digital signals are updated only after one minute in the flow computer. what may be the cause of delay in communication? Flow computer is having a scanning period of less than 1 sec.
Draw symbols of the following :
how to work MIL contol valve posistioner ?
you are on site,the plant trips,you are approached by operations,what do you do?
To become an Instrument DESIGN engineer, is there any softwares or training to become Instrument Design engineer, plz suggest me, Iam very much interested in designing.
wich is coming the first HAZOP OR SIL
how will you check torque value during Factory acceptance Test for control valve/ESD ON/OFF VALE how will you confirm this torque value is being correct, Which document will you be refer.