Answer Posted / banambar pradhan
in cement conc., if water cement ratio excess in conc. then
during the period of casting , aggregate goes down and
cement slurry goes up. this process is called laitance
| Is This Answer Correct ? | 14 Yes | 3 No |
Post New Answer View All Answers
what is Bearing Capacity,How to determine it?
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
what is Brest Wall?
While doing civil foundation of machinery. How will you process for it? & We also fixing plates at top surface of foundation, then what is the procedure?
how many types of survey and what are levelling instrument?
five benefits of using standard terminology in the measurement process
what is the difference b/w full length and cutting length?
What is the compressive strength of fly ash bricks?
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
How can you achieve soil enforcement?
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
Define What are the uses of alloys in daily life and how are alloys made?
how can we calculate steel value, depending on load