what is steel consumption for high rise building column,
beam, slab,footing
Answer Posted / s.k.roy
Based on experience the Consuption for a Building of 10-15
Storey :
Beams 125-140 Kg per cu.m of Concrete
Slabs 80-100 Kg per cu.m of Concrete
Columns 350-400 kg per cu.m of concrete
Footings100-125 Kg per cu.m
In general for a Eartquake Resistant Str in Zone 3/4 the
steel consumption can vary between 6.5 to 7.5 Kg per
sq.feet of Constructed area
Is This Answer Correct ? | 29 Yes | 7 No |
Post New Answer View All Answers
What is the outturn of Ceiling plastering
what are the types of design? which type of method is used at what type of design & why?
what is the type of earthing
Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
How to calculate plastering for elevated water storage tank
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
important question on stones
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.
what are the Task work of different labour.?
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
for pretensioning which will yield first and same for post tensioning?
Aptitude, reasoning, quants, verbal and technical question
Why are the bolts that hold steel rails together in oval holes?