how commission a transmitter evev plant is already running
Answer Posted / ashish namdev, bina refinery
when plant is running that time any Tx can be commission but
few precautions need to follow-
1. all interlocks which is related with Tx to be checked &
put it in bypass.
2. Check all process parameters in field.
3. If these all conditions are healthy then Tx can be lineup
or commission.
4. Check all settings, ranges etc.
5. After commission Tx interlock take in line.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
What is force balance principle? State some of its’ advantages.
Draw a P& ID showing – orifice flange, plate, dp transmitter, isolation & bypass valves and tubing.
Which type of diaphragm use in costic line, dm water line, natural gas line, oil line?
What is the working principle of the magnetic meter?
Define the difference between a stable versus an unstable controlled system and some of the tools you might use to be able to detect when this is happening and assumptions used for control system application design that could contribute to instability
Turbidity analyzer working principle ?
What is the difference between modbus,fieldbus & profibus
wich is coming the first HAZOP OR SIL
Definition of reverse and acting controllers:
i am having information technology branh ....... can i prepare for psu exam
how to calibrate corollaries (Mass flow meter)?
Why even multiple power supplu r used in instrumentation system?
What are continuances of connecting earthing and shield of branch cables (instrument to Junction box), at the same earthing pot provided on JB? Is it ok, or may produce some problem?
tell me the field & lab calibration procedure step by step with diagram of pressure gauge, pressure switch, pressure transmitter, temperature switch, level switch, flow switch, flow transmitter, temperature transmitter, temperature indicator, flow indicator, level indicator, control valve, thermocouple, pressure indicator (digital & analogue),
What are the application of bernoulli’s theorem?