what is advantages and disadvantages of the Waterfall Model
and V-Model
Answer Posted / mercy
In the traditional waterfall model, testing is done at the
end of the life cycle. The errors found at the later stages
are very expensive to fix. This has given an idea to V
model where in verification and validation are done at each
stage of SDLC to avoid errors/defects getting cascaded to
the other level. In other words V model aims for Stage
containment.
| Is This Answer Correct ? | 35 Yes | 7 No |
Post New Answer View All Answers
What do you mean by Cause Effect Graphing? in which standard its mentioned?
In our project, we use Withdrawal Indent, we are confused to use heading as "Withdrawal Indent" or "Withdraw Indent". Please suggest me which one to use ASAP, Thanks in advance
Different types of design diagrams that supports to write test cases ?
What is Test Design?
what comments have u given in peer review? tell me at least 3 comments what u have given? july27 brahma412@yahoo.co.in
Hello everybody, How many people do you think one sprint team can have in average?
1) Test summary contains ? 2) Requirement Tracebility means ? 3) Test Effort contains ? 4) Test Planning Productivity ? 5) Metrics should be caluclated ? 6) Interest rate Rsik is a type ? 7) Test analysis and Design process task? 8) secured loan is a part of Liability (or) assest in a balance sheet? 9) Money Market means? 10) a ------ specifies all of the terms of a loan and the obligations borrower ? 11) what is a primary market is ? 12) Quality of Testing measure with ? 13) Company has a share with facevalue 10 rs/- and NAV of 37 after comapny has given Dividend of 35 % then How much NAV become ? ( I don't know what is NAV means, question overall Idea I am giving not 100% perfect ) the potions for these are 1) 33 2) 33.50 3) 37 4) 42 14) one compay has taken 10 million loan from a bank for a Interest rate is 10 % and base amount is 0.4% so how much they had paid monthly Emi ? they provideansews like 1) 100000 2) 114000 3) 140000 4) 104000 Remaing questions I not remember.
Write down ten test cases for below scenario: Increase the day by 1 and date format should be mm/dd/yyyy Conditions are : date should not be greater then 31 and date<1 month should not be greater then 12 and month<1 year should not be greater then 10000 and year<1 Thanks in advance
i want manual and automation test cases and interview questions
what are the advantages of manual and automation testing ? and which one would u term as efficent testing and effective testing ?pls do reply thankx in advance
Can you explain process areas in cmmi?
how will the test plan is pepared in ur organisation>?
What are bug leakage and bug release?
How can you define state tanstion testing aswell decesion testing with examples.how you can differ them too??
how to creat 2 test plan in 2 different environment exp:tour and travel