why shear reinforcement is not provided in the design of
footing?
Answer Posted / rajesh shirakol
Some times one way shear failure is the primary failure. When the bending stresses(M/z) are high then the shear induced is also high.
I would recommend every footing design for one way as well as two way (punching) shear analysis.
| Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
what is mc arther pile?
how to convert cement, sand aggregate quantity from M3 to kg with full description?
Can inverted beams used in pipes during construction?
How many % we consider for lap for reinforcement for estimates
What are the advantages of building a dam on the river nile?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
what is diffrence between catchment area,watershed and basin?
How do we determine the specific gravity of a cement?
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
What is .Dwg?
is basic cost of the material includes tax?
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
how much percent are used 20mm,10mm?
What is the maximum strength of cub compress strength in one cub testing