Answer Posted / mukarram
I Think there is no Difference between the two.. both are
the same..
Formwork is the term given to either temporary or permanent
moulds into which concrete or similar materials are poured.
In the context of concrete construction, the falsework
supports the shuttering moulds.
and same for shuttering also...
| Is This Answer Correct ? | 12 Yes | 12 No |
Post New Answer View All Answers
What do we mean by partial moment release ??
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
What are the disadvantages while using stone dust as filler in pavements?
How can we convert weight batch to volume batch for m30 mix
what's the formula for calculate pcc for matt(45mm aggregate)?
Describe the sections included in a typical bill of quantities
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
How to get MEP technical,instaaltion & testing data for interview?
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
what is the meaning of 40/20 src
What black man invented the clothes dryer?
How can we make a hole in a solid rectangle using solidsworks?
The largest size of paper used in plotter to print the drawing made by Autocad .