Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

WE HAVE A LOAD OF 55KW MOTOR ITS VOLTS 380 3PH AND ITS
TAKING 100AMPS (ITS FULL LOAD IS 105AMPS)AND ITS CABLE IS
4CX50SQMM ,NOW ITS GETTING ABNORMAL HEATUP IN CABLE,PLZ
TELL WHY ITS HEAT-UP?(CABLE LENGTH IS 15 METERS ONLY)

Answer Posted / k.prakashchandra

Further, if the armour is earthed at both ends ,there is
likelihood of cable getting heated.

Is This Answer Correct ?    1 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What was the Dg set radiator and lube oil temperatures trip in ACB

1835


Why did lightening arrestor solid copper rod head is sharp on mobile tower top?

2023


Why is it prefer to initiate circuit breaker failure by "86" lockout relay not by "94" tripping relay ?!

1800


Is the theorem applicable to ac sources?

1046


When lag/lead/lag-lead compensation is employed?

1191


diff. between tension mode & speed mode

2341


What should be the protection scheme for a 15kw, 3-phase motor working in a lathe machine.

2069


I have experienced electrical maintenance HT ,but I completed be ECE ....can I apply c license or not ???? Pls help me friend s...

1573


How generating electric power export to grid from the generating station ?

1883


Why using synchronising methed in DG's sets?

2214


A 7 storey building has a floor area of 35,000sq.ft on each storey. On the ground floor 11KV electrical sub-station is to be erected. A load of 3kw for every 400sq.ft (p.f is 0.8) is proposed for each floor. fire pump 7.5hp, water pump 5hp, lift 2 nos, each 10hp and 20shop load of each shop is 5kw. calculate a. load each floor b. total load of building c. L.T feeders for aech floor and from transformer to main. d. distribution diagram e. capacity of sub-station/capacitor bank f. line diagram

2818


What is sink and source?

1191


can you any one give exact mathematical relation between AC current and DC current?

2004


state working of halogen lamp?

1824


Does the direction of rotation of d.c. Shunt motor would get reversed if the armature current and field current both are reversed?

1162